Project Management Professional (PMP) Exam Practice – Question0530

Which process develops options and actions to enhance opportunities and reduce threats to project objectives?


A.
Identify Risks
B. Control Risks
C. Plan Risk Management
D. Plan Risk Responses

Correct Answer: D