Project Management Professional (PMP) Exam Practice – Question0541

Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?


A.
Organizational process updates
B. Quality metrics
C. Change requests
D. Quality control measurements

Correct Answer: B