Project Management Professional (PMP) Exam Practice – Question0567

Which Process Group includes the Manage Stakeholder Engagement process?


A.
Executing
B. Planning
C. Monitoring and Controlling
D. Initiating

Correct Answer: A

Explanation:

Explanation:
Reason: Control Stateholder Engagement is in the Monitoring and Control Process.