Project Management Professional (PMP) Exam Practice – Question0571

Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (WBS) to give structure to the decomposition of the scope?


A.
Activity network diagrams
B. Affinity diagrams
C. Matrix diagrams
D. Interrelationship digraphs

Correct Answer: B