What does a CPI value greater than 1.0 indicate?


A.
Cost right at the estimated value
B. Cost under the estimated value
C. Cost right at the actual value
D. Cost over the estimated value

Correct Answer: B

Tagged Project Management Professional (PMP) Exam Practice, Question 0650