Project Management Professional (PMP) Exam Practice – Question0665

The correct equation for schedule variance (SV) is earned value:


A.
minus planned value [EV -PV].
B. minus actual cost [EV -AC].
C. divided by planned value [EV/PV],
D. divided by actual cost [EV/AC].

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0665