Skip to content

Project Management Professional PMP Mock Exam Practice

  • Project Management Professional (PMP)

Tag: Question 0674

Project Management Professional (PMP) Exam Practice – Question0674

Approved change requests, approved corrective actions, and updates to organizational process assets are all outputs of which project management process?


A.
Risk response planning
B. Manage stakeholders
C. Scope definition
D. Performance reporting

Correct Answer: B

Tagged Project Management Professional (PMP) Exam Practice, Question 0674