Project Management Professional (PMP) Exam Practice – Question0676


Which of the following is the correct network diagram for the table?


A.
Begin-A-C-D-E-End-B-D
B. Begin-A-B-C-D-E-End
C. Begin-A-B-D-E-End A-C-D
D. Begin-A-C-D-E-End-B-C

Correct Answer: A