Tag: Question 0679

Project Management Professional (PMP) Exam Practice – Question0679

A risk may be graded into different priorities by which process?


A.
Risk monitoring and controlling
B. Risk response planning
C. Qualitative risk analysis
D. Quantitative risk analysis

Correct Answer: C