Skip to content

Project Management Professional PMP Mock Exam Practice

  • Project Management Professional (PMP)

Tag: Question 0704

Project Management Professional (PMP) Exam Practice – Question0704

Information distribution involves making needed information available to project stakeholders in a timely manner. What is an output from information distribution?


A.
Earned value analysis
B. Trend analysis

C. Project records
D. Performance reviews

Correct Answer: C

Tagged Project Management Professional (PMP) Exam Practice, Question 0704
Download all of these questions as Printable PDF for $19.50
Exam Practice Tests
sponsored