A project manager needs to deliver the project 2 weeks before the planned date without changing the scope. Which of the following techniques may be applied to reevaluate the schedule?


A.
What-if scenario analysis
B. Critical chain method
C. Schedule crashing
D. Resource leveling

Correct Answer: C