Project Management Professional (PMP) Exam Practice – Question0731

The three types of estimates that PERT uses to define an approximate range for an activitys cost are:


A.
Parametric, most likely, and analogous.
B. Least likely, analogous, and realistic.
C. Parametric, optimistic, and pessimistic.
D. Most likely, optimistic, and pessimistic.

Correct Answer: D