Skip to content

Project Management Professional PMP Mock Exam Practice

  • Project Management Professional (PMP)

Tag: Question 0741

Project Management Professional (PMP) Exam Practice – Question0741

Team performance assessments is an output of which of the following processes?


A.
Develop Human Resource Plan
B. Perform Quality Control
C. Develop Project Team
D. Manage Project Team

Correct Answer: C

Tagged Project Management Professional (PMP) Exam Practice, Question 0741