Skip to content

Project Management Professional PMP Mock Exam Practice

  • Project Management Professional (PMP)

Tag: Question 0756

Project Management Professional (PMP) Exam Practice – Question0756

Project Management Process Groups are linked by:


A.
the outputs they produce
B. discrete or one-time events
C. the project management plan
D. common tools and techniques

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0756