A projects schedule indicates that activity A has a duration of five days, activity B has a duration of two days, and activity C has a duration of three days. Activity D has mandatory dependencies on activities A, B, and C. 
What is the free float of activity B?
A. 10 days 
B. 5 days 
C. 3 days 
D. 2 days