Skip to content

Project Management Professional PMP Mock Exam Practice

  • Project Management Professional (PMP)

Tag: Question 0877

Project Management Professional (PMP) Exam Practice – Question0877

What should a project manager use to determine next steps when safety issues are identified?


A.
Variance analysis
B. Earned value management (EVM)
C. Root cause analysis
D. Corrective action

Correct Answer: D

Tagged Project Management Professional (PMP) Exam Practice, Question 0877
Download all of these questions as Printable PDF for $19.50
Exam Practice Tests
sponsored