Project Management Professional (PMP) Exam Practice – Question0945

Activity cost estimates and the project schedule are inputs to which Project Cost Management process?


A.
Estimate Costs
B. Control Costs
C. Plan Cost Management
D. Determine Budget

Correct Answer: D