Project Management Professional (PMP) Exam Practice – Question0954

Which Perform Quality Assurance tool or technique is used to identify a problem, discover the underlying causes that lead to it, and develop preventative actions?


A.
Inspection
B. Quality audits
C. Design of experiments
D. Root cause analysis

Correct Answer: D