Skip to content

Project Management Professional PMP Mock Exam Practice

  • Project Management Professional (PMP)

Tag: Question 0957

Project Management Professional (PMP) Exam Practice – Question0957

The following chart contains information about the tasks in a project.

Based on the chart, what is the cost variance (CV) for Task 6?


A.
-2,000
B. 0
C. 1,000
D. 2,000

Correct Answer: D

Tagged Project Management Professional (PMP) Exam Practice, Question 0957
Download all of these questions as Printable PDF for $19.50
Exam Practice Tests
sponsored