Skip to content

Project Management Professional PMP Mock Exam Practice

  • Project Management Professional (PMP)

Tag: Question 0977

Project Management Professional (PMP) Exam Practice – Question0977

Which Process Group's purpose is to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes?


A.
Monitoring and Controlling
B. Initiating
C. Planning
D. Executing

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0977