Project Management Professional (PMP) Exam Practice – Question0978

Work performance information and cost forecasts are outputs of which Project Cost Management process?


A.
Estimate Costs
B. Plan Cost Management
C. Determine Budget
D. Control Costs

Correct Answer: D