Project Management Professional (PMP) Exam Practice – Question0985

Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project?


A.
Analogous
B. Parametric
C. Bottom-up
D. Top-down

Correct Answer: A