Project Management Professional (PMP) Exam Practice – Question0989

Which Develop Schedule tool and technique produces a theoretical early start date and late start date?


A.
Critical path method
B. Variance analysis
C. Schedule compression

D. Schedule comparison bar charts

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0989