Skip to content

Project Management Professional PMP Mock Exam Practice

  • Project Management Professional (PMP)

Tag: Question 0993

Project Management Professional (PMP) Exam Practice – Question0993

Change requests are an output from which Project Integration Management process?


A.
Direct and Manage Project Execution
B. Develop Project Management Plan
C. Close Project
D. Develop Project Charter

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 0993