Project Management Professional (PMP) Exam Practice – Question1007

A tool and technique used during the Perform Qualitative Risk Analysis process is:


A.
risk data quality assessment.
B. variance and trend analysis.
C. data gathering and representation techniques.
D. risk audits.

Correct Answer: A

Tagged Project Management Professional (PMP) Exam Practice, Question 1007