Project Management Professional (PMP) Exam Practice – Question1021

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?


A.
Applying calendars
B. Resource leveling
C. Resource planning
D. Resource conflict management

Correct Answer: B