Project Management Professional (PMP) Exam Practice – Question1029

The total of the planned value (PV) is also known as:


A.
work breakdown structure (WBS).
B. schedule target.
C. performance measurement baseline (PMB).
D. earned value baseline.

Correct Answer: C