Project Management Professional (PMP) Exam Practice – Question1043

Which process involves aggregating the estimated costs of the individual schedule activities or work packages?


A.
Cost baseline
B. Cost forecasting
C. Cost variance
D. Cost budgeting

Correct Answer: D