What is the minimum a project schedule must include?


A.
Variance analysis
B. A planned start date and a planned finish date for each schedule activity
C. A critical path diagram
D. Critical chain analysis

Correct Answer: B

Tagged Project Management Professional (PMP) Exam Practice, Question 1049