Skip to content

Project Management Professional PMP Mock Exam Practice

  • Project Management Professional (PMP)

Tag: Question 1050

Project Management Professional (PMP) Exam Practice – Question1050

When does risk monitoring and control occur?


A.
At project initiation
B. During work performance analysis
C. Throughout the life of the project
D. At project milestones

Correct Answer: C

Tagged Project Management Professional (PMP) Exam Practice, Question 1050
Download all of these questions as Printable PDF for $19.50
Exam Practice Tests
sponsored