Project Management Professional (PMP) Exam Practice – Question1064

Which Activity Duration Estimating technique incorporates additional timing for contingency purposes?


A.
Analogous Estimating
B. Expert Judgment
C. Optimistic Estimates
D. Reserve Analysis

Correct Answer: D