Project Management Professional (PMP) Exam Practice – Question1075

Which of the Project Time Management processes analyzes activity sequencing, durations, resource requirements, and schedule constraints?


A.
Estimate Activity Durations
B. ControlSchedule
C. Sequence Activities
D. Develop Schedule

Correct Answer: D