Project Management Professional (PMP) Exam Practice – Question1119

During a project review, the construction manager reports that the concrete production rate has changed over the last three months. What analysis should be conducted?


A.
Earned value (EV)
B. Critical path
C. Trend
D. Cost

Correct Answer: C