Project Management Professional (PMP) Exam Practice – Question1166

Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?


A.
Issue log
B. Change log
C. Expert judgment
D. Change requests

Correct Answer: B

Tagged Project Management Professional (PMP) Exam Practice, Question 1166