Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?


A.
Perform Quality Assurance
B. Direct and Manage Project Work
C. Monitor and Control Project Work
D. Perform Integrated Change Control

Correct Answer: D

Tagged Project Management Professional (PMP) Exam Practice, Question 1200