Project Management Professional (PMP) Exam Practice – Question1221

Which is the correct formula for calculating expected activity cost for three-point estimating?


A.
Ce =(C0 +6Cm +Cp)/4
B. Ce =(6C0 +Cm +Cp)/4
C. Ce =(C0 +4Cm +Cp)/6
D. Ce =(C0 +C, +4Cp)/6

Correct Answer: C