Project Management Professional (PMP) Exam Practice – Question1232

Exhibit A is an example of which of the following types of Sequence Activities?


A.
Activity-on-arrow diagramming
B. Precedence diagramming
C. Project schedule network diagramming
D. Mathematical analysis diagramming

Correct Answer: C