Project Management Professional (PMP) Exam Practice – Question1334

Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?


A.
Crashing
B. Fast tracking
C. Leads and lags adjustment
D. Parallel task development

Correct Answer: B