Which following item is NOT an input to control scope?


A.
Requirements traceability matrix

B. Work performance data
C. Deliverables
D. Scope management plan

Correct Answer: C

Explanation:

Explanation:
Verified deliverables that are completed and checked for correctness are inputs to validate scope.