A challenge of earned value management is predicting percent complete. The simplest formula to use to calculate EV is______________
A. 0/100 rule
B. 50/50 rule
C. (Percent complete)h budget at completion)
D. Milestone method
A. 0/100 rule
B. 50/50 rule
C. (Percent complete)h budget at completion)
D. Milestone method