Skip to content

Project Management Professional PMP Mock Exam Practice

  • Project Management Professional (PMP)

Tag: Question 1924

Project Management Professional (PMP) Exam Practice – Question1924

Which of the following would a team create as a result of using a change control system?


A.
Change requests
B. Approved changes
C. Impact analysis
D. Signoff

Correct Answer: B

Tagged Project Management Professional (PMP) Exam Practice, Question 1924
Download all of these questions as Printable PDF for $19.50
Exam Practice Tests
sponsored