Project Management Professional (PMP) Exam Practice – Question1973

Calculate the standard deviation for the following: Pessimistic=50, Optimistic=10, Realistic=24.

A.
26

B. Not enough information
C. 5.67
D. 6.667

Correct Answer: D

Tagged Project Management Professional (PMP) Exam Practice, Question 1973