The Project Manager is reviewing testing output. Generally, the data looks good. He does observe seven consecutive data points on one side of the mean in a couple of areas on the control chart. 
What is this called?
A. A violation of the Seven Run Rule 
B. Lucky seven gets eleven 
C. Acceptable measurements 
D. Too loose of specification limits