AWS Certified Advanced Networking – Specialty ANS-C00 – Question271

Your company has a highly-available Direct Connect solution that utilizes two datacenters. Each datacenter was initially configured with one four-connection LAG and one standard DX connection. How many LOA documents have been requested and completed for this configuration?

A.
1
B. 4
C. 2
D. 10

Correct Answer: B

Explanation:

Explanation:
Only one LOA document is required for each physical connection. The logical connections in the LAG do not need separate LOAs, but they do have separate pages.