A Development team is working on a serverless application in AWS. To quickly identify and remediate potential production issues, the team decides to roll out changes to a small number of users as a test before the full release. The DevOps Engineer must develop a solution to minimize downtime and impact. Which of the following solutions should be used to meet the requirements? (Choose two.)

A.
Create an Application Load Balancer with two target groups. Set up the Application Load Balancer for Amazon API Gateway private integration. Associate one target group to the current version and the other target group to the new version. Configure API Gateway to route 10% of incoming traffic to the new version. As the new version becomes stable, configure API Gateway to send all traffic to the new version and detach the old version from the load balancer.
B. Create an alias for an AWS Lambda function pointing to both the current and new versions. Configure the alias to route 10% of incoming traffic to the new version. As the new version is considered stable, update the alias to route all traffic to the new version.
C. Create a failover record set in AWS Route 53 pointing to the AWS Lambda endpoints for the old and new versions. Configure Route 53 to route 10% of incoming traffic to the new version. As the new version becomes stable, update the DNS record to route all traffic to the new version.
D. Create an ELB Network Load Balancer with two target groups. Set up the Network Load Balancer for Amazon API Gateway private integration Associate one target group with the current version and the other target group with the new version. Configure the load balancer to route 10% of incoming traffic to the new version. As the new version becomes stable, detach the old version from the load balancer.
E. In Amazon API Gateway, create a canary release deployment by adding canary settings to the stage of a regular deployment. Configure API Gateway to route 10% of the incoming traffic to the canary release. As the canary release is considered stable, promote it to a production release

Correct Answer: DE