AWS Certified Solutions Architect – Professional SAP-C01 – Question329

Identify a correct statement about the expiration date of the "Letter of Authorization and Connecting Facility Assignment (LOACFA)," which lets you complete the Cross Connect step of setting up your AWS Direct Connect.

A.
If the cross connect is not completed within 90 days, the authority granted by the LOA-CFA expires.
B. If the virtual interface is not created within 72 days, the LOA-CFA becomes outdated.
C. If the cross connect is not completed within a user-defined time, the authority granted by the LOA- CFA expires.
D. If the cross connect is not completed within the specified duration from the appropriate provider, the LOA-CFA expires.

Correct Answer: A

Explanation:

Explanation: An AWS Direct Connect location provides access to AWS in the region it is associated with. You can establish connections with AWS Direct Connect locations in multiple regions, but a connection in one region does not provide connectivity to other regions. Note: If the cross connect is not completed within 90 days, the authority granted by the LOA-CFA expires.
Reference:
http://docs.aws.amazon.com/directconnect/latest/UserGuide/Colocatio…