Which of the following is the BEST reason to follow the change management process in this scenario?
A. Owners can be notified a change is being made and can monitor it for performance impact.
B. A risk assessment can be performed to determine if the software is needed.
C. End users can be aware of the scope of the change.
D. A rollback plan can be implemented in case the software breaks an application.