A department manager submits a help desk ticket to request the migration of a printer's port utilization from USB to Ethernet so multiple users can access the printer. This will be a new network printer, thus a new IP address allocation is required. Which of the following should happen immediately before network use is authorized?
A. Document the date and time of the change.
B. Submit a change request form.
C. Determine the risk level of this change.
D. Request an unused IP address.
A. Document the date and time of the change.
B. Submit a change request form.
C. Determine the risk level of this change.
D. Request an unused IP address.