CompTIA Cloud+ CV0-003 – Question038

A company just successfully completed a DR test and is ready to shut down its DR site and resume normal operations. Which of the following actions should the cloud administrator take FIRST?

A.
Initiate a failover.
B. Restore backups.
C. Configure the network.
D. Perform a failback.

Correct Answer: D