CompTIA Network+ N10-008 – Question131

The management team has instituted a 48-hour RTO as part of the disaster recovery plan. Which of the
following procedures would meet the policy's requirements?


A.
Recover all systems to a loss of 48 hours of data.
B. Limit network downtime to a maximum of 48 hours per year.
C. Recover all systems within 48 hours.
D. Require 48 hours of system backup maintenance.

Correct Answer: C

Explanation: